Monday, 25 April 2011

Week 16: Foundation is fast and furious here/ thriller in the price

The Me-Perustukset team have tried to install the frames for pouring concrete last week Friday. Firstly, they had to wait a day as there was a problem with the steel delivery. Then, our foreman decided to go and visit the site and inspect the foundation to make sure that there is enough steel placed in the frames before pouring concrete.

Unfortunately he came all the way from Lohja in vain as the steel was not yet placed in the frames due to the delays of the steel delivery. He could have called Me-perustukset first and ask if the site is ready for inspection instead of coming and wasting his time...better communication would be nice! Especially as we're paying for foreman's' visits :).

Anyway by Tuesday the frames for the plinth beams (sokkeli) were ready for inspection.The foreman did notice one error as the middle floor frame was misplaced (in mirror image instead) and then the foundation crew made the necessary changes in time.

Inspecting the premises :)

steel reinforcements before concrete was poured

terrace

ventilation hole

the entrance terrace
And after a while at 8 pm same day, the trucks with concrete arrived and concrete started pouring...











 Then the concrete was left to dry for one day and on Thursday the frames were removed and the prefabricated floor beams were brought in onto 40-tonnes truck. This was the one we were afraid of... Will the road last or not the heavy weight...

And on Thursday, the super heavy truck came, road was ready and wide enough...but the truck driver was probably not very experienced as he took a too narrow turn from main road to our land and this is what happened...







A super heavy assistance truck was called in to pull the truck with concrete beams out of the ditch.

3 hours were lost but in the end the rescue was successful and the team installed the floor beams and look what became of it...

our house's got FOUNDATION :)
The crawl in space under the foundation

Then the day continued with the last act taking place...
The empty truck was not able to reverse up the hill to the main road...and then another  assistance truck was called to help in... (excuse the video quality)


What a thriller Thursday it's been!  But in the end the foundation crew was able to finish and leave at about 4 pm, I guess ready to celebrate something. Easter?

See also our other post on foundation:
http://project-eco-house-finland.blogspot.com/2011/03/its-question-of-foundation.html

Thursday, 24 March 2011

week 12: Building permit was approved 22-Mar-2011

Yes. Bulding permit was approved. Work can now start properly.
Here are some pictures from this week.
 

The house and garage exact spots were marked by the engineers from Kirkkonummi municipality.

The house ground has now been prepared for the steel pillars (paalutus) that will be knocked into the ground for 7-10 meters until they reach solid ground. The pillars will installed next week.
There is now electricty for the works.

Spring is not yet here but weather was beautiful this Saturday morning when I ran/ walked from home to the land and back (about 8 km in total).

Saturday, 12 March 2011

It's a question of Foundation

The land where the house will be built is made of clay (savimaa - old bottom of the sea) and therefore the foundation has to be made on pillars (7-10m long) that are standing on the firmer ground beyond the clay. Then on top of the pillars will be put hollow core floor beams of 26.5cm thick. Then insulating material 25 cm (Expanded polystyrene (EPS)) and a concrete floor of 8-10 cm thick into which also the floor heating pipes will be installed. Below is a picture I've taken of the way it sort of looks although our insulation is bigger than in the picture where I guess is only 20cm and the side plinth beam will be from solid concrete.

The technical drawing for our foundation wall structure looks like below (there's crawling space under the floor of at least 0.8m):

 The foundation is not coming from Lapponia house so we had to get the whole package from another company.

We had asked quite a few companies for quotations but not many offer ther complete package ( pillars, beams, insulation, concrete floor casting, etc). We got basically offers from 2 companies for the complete package: Basso (via Lapponia sales agent) and Me-Perustukset. The initial Basso offer was 50 % (!) more expensive than the one from Me-perustukset. Only after Basso found out the fact that we got a much cheaper offer from ME, Basso also came down to a much similar price. But then we did not want to consider their offer anymore as we felt Basso initially tried to ripp us off. Also Basso's offer did not include making the ventilation holes and also it requires to pay separately if the foundation/ concrete needs heating during the colder season.

The round prices of the offer we accepted from Me-perustukset for our foundation and pillars  (materials and installation) including the terace were:
- plinth beams and floor beams (sokkelipalkki ja ontelolaatta) - 18000
- steel pillars (teräspaalutus) 112m  - 4500
- concrete floor casting  - 3000
- steel net and EPS insulation - 2700
- foundation and water drainage design - 1200

So far I have been happy with the service from Me-perustukset and the sales person speaks very well english (Mikko Kuoppa - Update Nov 2011 - Mikko left the company we were told).
Even more of a pleasant surprise was that the during the design fase, the Me-perustukset planner came with a proposal for a different set up of the foundation which needed less plinth beams and steel pillars than were quoted in the initial offer and therefore we got a reduction of 2000 euro in the total price!

See also our other post about foundation:
http://project-eco-house-finland.blogspot.com/2011/04/week-16-foundation-is-fast-and-furious.html

UPDATE Nov 2011: 
We concluded not to recommend anymore ME-perustukset due to the fact that they have been delaying our garage foundation for very long during the summer and the contact person from ME was saying many times that they come next week, and then next week etc. And when they came they have made the garage pillars too weak. Our head-designer / vastaava meestari asked them to correct it and after couple more weeks they came and made the pillars again but then once again they were wrong (not fulfilling the standards). ME-perustukset contact person mentioned that the garage foundation was being made by a subcontractor of theirs but that does excuse them, I would say.  The third time went right, after our head-designer explained them on the spot what went wrong.
Now, due to delays and frost coming up, we decided to postpone the finalization of the foundation until next spring...